on this page
As the mighty Peace River flows from northern British Columbia (BC) to Alberta, its waters carry incredible potential to help fill our need for clean energy.
The Site C project is the third project on the BC side that taps into the that potential. When complete, its generators will make enough power to run 450,000 homes each year for the next century. Together, the three Peace River projects will generate around 40% of BC Hydro’s power.
Situated about 7 kilometres southwest of Fort St. John, the Site C project has been under construction since 2015. The expected completion date is 2025. As the third project on the river system, Site C gains significant efficiencies by taking advantage of water already stored in the Williston Reservoir behind the W.A.C. Bennett Dam. This means that Site C will generate approximately 35% of the Bennett Dam’s energy, but with only 5% of the reservoir area.
AtkinsRéalis is the engineer of record for the core structures, including the diversion tunnels, excavations and earthfill dam, roller-compacted concrete (RCC) buttress, generating station and spillways. Over the course of this project we provided engineering services, delivering feasibility studies and supervising geotechnical investigations, completed detailed design and provided technical support throughout construction.
What we’re building
- Stabilizing the north bank via a large excavation of unstable materials and flattening of slope.
- Constructing two temporary cofferdams across the main river channel and two 12.5 m diameter diversion tunnels to allow for the construction of the earthfill dam
- An earthfill dam approximately 1,050 m long and 60 m high above the riverbed. The dam comprises a central impervious core, core trench excavated to shale bedrock, a grout curtain along the floor of the core trench, filters on either side of the core, gravel drains on the downstream side of the core, and outer shells of sands and gravels.
- An approach channel with an impervious lining along the channel and an 8 m high berm running along the middle.
- An 800-m-long RCC buttress to enhance seismic protection. The RCC buttress supports the valley's south wall, provides an abutment for the earthfill dam and is a foundation for the generating station and spillway.
- Six power intakes and penstocks with vertical lift gates.
- A generating station comprising six 183 MW vertical Francis generating units.
- A temporary diversion consisting of twin tunnels and cofferdams.

Innovation and challenges
Please note that you are now leaving the AtkinsRéalis website (legal name: AtkinsRéalis Group inc.) and entering a website maintained by a third party (the "External Website") and that you do so at your own risk.
AtkinsRéalis has no control over the External Website, any data or other content contained therein or any additional linked websites. The link to the External Website is provided for convenience purposes only. By clicking "Accept" you acknowledge and agree that AtkinsRéalis is not responsible, and does not accept or assume any responsibility or liability whatsoever for the data protection policy, the content, the data or the technical operation of the External Website and/or any linked websites and that AtkinsRéalis is not liable for the terms and conditions (or terms of use) of the External Website. Further, you acknowledge and agree that you assume all risks resulting from entering and/or using the External Website and/or any linked websites.
BY ENTERING THE EXTERNAL WEBSITE, YOU ALSO ACKNOWLEDGE AND AGREE THAT YOU COMPLETELY AND IRREVOCABLY WAIVE ANY AND ALL RIGHTS AND CLAIMS AGAINST ATKINSRÉALIS, AND RELEASE, DISCHARGE, INDEMNIFY AND HOLD HARMLESS ATKINSRÉALIS, ITS OFFICERS, EMPLOYEES, DIRECTORS AND AGENTS FROM ANY AND ALL LIABILITY INCLUDING BUT NOT LIMITED TO LIABILITY FOR LOSS, DAMAGES, EXPENSES AND COSTS ARISING OUT OF OR IN CONNECTION WITH ENTERING AND/OR USING THE EXTERNAL WEBSITE AND/OR ANY LINKED WEBSITES AND ANY DATA AND/OR CONTENT CONTAINED THEREIN.
Such waiver and release specifically includes, without limitation, any and all rights and claims pertaining to reliance on the data or content of the External Website, or claims pertaining to the processing of personal data, including but not limited to any rights under any applicable data protection statute. You also recognize by clicking “Accept” that the terms of this disclaimer are reasonable.
The information provided by Virtua Research cited herein is provided “as is” and “as available” without warranty of any kind. Use of any Virtua Research data is at a user’s own risk and Virtua Research disclaims any liability for use of the Virtua Research data. Although the information is obtained or compiled from reliable sources Virtua Research neither can nor does guarantee or make any representation or warranty, either express or implied, as to the accuracy, validity, sequence, timeliness, completeness or continued availability of any information or data, including third-party content, made available herein. In no event shall Virtua Research be liable for any decision made or action or inaction taken in reliance on any information or data, including third-party content. Virtua Research further explicitly disclaims, to the fullest extent permitted by applicable law, any warranty of any kind, whether express or implied, including warranties of merchantability, fitness for a particular purpose and non-infringement.
The consensus estimate provided by Virtua Research is based on estimates, forecasts and predictions made by third party financial analysts, as described above. It is not prepared based on information provided by AtkinsRéalis and can only be seen as a consensus view on AtkinsRéalis' possible future results from an outside perspective. AtkinsRéalis has not provided input on these forecasts, except by referring to past publicly disclosed information. AtkinsRéalis does not accept any responsibility for the quality or accuracy of any individual or average of forecasts or estimates. This web page contains forward-looking statements based on current assumptions and forecasts made by third parties. Various known and unknown risks, uncertainties and other factors could lead to material differences between AtkinsRéalis' actual future results, financial situation, development or performance, and the estimates given here.

-
Markets
Power & renewables
-
Location
Fort St John, British Columbia
-
Client
BC Hydro British Columbia Hydro and Power Authority (B.C. Hydro)
-
Collaborators
MOU to work as an integrated team with Klohn Crippen Berger (KCB)
-
Completion date
2025

Vinod Batta
Market Lead, Power & Renewables, Vancouver, Canada contact form
Downloads
Trade releases