While there has been much speculation about what the Building Safety Act will mean for existing procurement practices, what is certain is that current process will need to change to reflect the new requirements, particularly on Higher Risk Buildings (HRBs).
The one thing the Building Safety Regulator (BSR) has been clear on is that the current practice of starting works on site whilst other key elements of the design are progressed will not be acceptable.
The BSR has said it cannot see the current process working in the new regime because design occurring at the same time as construction will not be viable. Design and build will have to change.
Single stage design and build
It raises the key question that if design needs to be progressed to satisfy Building Control before works start on site, does that mean the end of single stage D&B?
The principles of projects are essentially unchanged in that a design needs to be progressed and built that meets Building Regulations at completion. The main changes in risk profile are the point at which certainty around compliance with building regulations is achieved, the bodies capable of providing that approval, and who takes the contractual risk of delays in approval from the BSR. The main issue is that historically this process typically happened concurrently with construction, and the risk of achieving building regulations approval was well understood, to the extent that the risks were able to be controlled and priced.
The newer regime will mean this moves to a position that could delay start of physical works on site. The counter to this is that works should progress much more smoothly once started as delays awaiting design information or sign off should not occur so readily. The main concern at present raised by contractors under a design and build contract is how the risk of delays from the statutory gateway approval process will be handled contractually.
Until more schemes have gone through the gateway process, providing clarity on what will and, more importantly, will not be acceptable to the BSR, and the time it is likely to take to gain gateway 2 approval, the likelihood of contractors willing to accept this risk will be very low. It is far more likely that contractors will seek to be engaged under a PCSA to gain Gateway 2 approval, before committing to a contract sum to deliver the build, leading to a natural move to two stage tendering.
The main concern here from clients is that this means they would be heavily invested in one contractor and could face inflated build costs at the final offer stage with the contractor knowing that restarting the process with another party would cost considerable time and money. Relationships and trust will be more critical than ever here and more collaborative working certainly looks to be the most viable way forwards.
Product availability
One scenario which has been raised by contractors as a key risk, is what happens if a specified product, or system designed and approved under gateway 2, is no longer available? If for example a supplier withdraws the product from the market, material availability means it cannot be procured in time, or the supplier ceases to trade. The most significant impact here is if these products were part of the external wall build up.
In these circumstances the contractor would be forced down the six week significant change route, and they are likely to want to see that risk covered off in contract terms.
Project handover and gateway 3
For HRBs at completion the project needs to go through the formal gateway 3 process before occupation. This is another key point as this is the time when clients are exposed to the maximum financing costs, before revenue starts to flow in to pay back loans. The statutory period here is eight weeks.
Little has been made of this to date as this is not the immediate focus for many trying to get their projects through gateway 2 and onto site, but we are already seeing clients trying to get this transferred into building contracts with PC linked to the completion certificate under the BSA.
Contractors are likely to push back on the statutory eight week determination period to avoid damages being linked to something that is outside of their ultimate control. So a balance is likely to be agreed on contracts to ensure contractors are not penalised for the failings of the BSR to meet the statutory period, but equally they are held accountable if they cause those delays due to poor information issued.
It is clear there are quite a few changes for the industry to grapple with, some of them may seem challenging to begin with, but that is why seeking expert advice and working collaboratively across the industry, will ensure a smoother transition to the working practices outlined in the act.
This article was first published by Building Magazine in January 2025
Please note that you are now leaving the AtkinsRéalis website (legal name: AtkinsRéalis Group inc.) and entering a website maintained by a third party (the "External Website") and that you do so at your own risk.
AtkinsRéalis has no control over the External Website, any data or other content contained therein or any additional linked websites. The link to the External Website is provided for convenience purposes only. By clicking "Accept" you acknowledge and agree that AtkinsRéalis is not responsible, and does not accept or assume any responsibility or liability whatsoever for the data protection policy, the content, the data or the technical operation of the External Website and/or any linked websites and that AtkinsRéalis is not liable for the terms and conditions (or terms of use) of the External Website. Further, you acknowledge and agree that you assume all risks resulting from entering and/or using the External Website and/or any linked websites.
BY ENTERING THE EXTERNAL WEBSITE, YOU ALSO ACKNOWLEDGE AND AGREE THAT YOU COMPLETELY AND IRREVOCABLY WAIVE ANY AND ALL RIGHTS AND CLAIMS AGAINST ATKINSRÉALIS, AND RELEASE, DISCHARGE, INDEMNIFY AND HOLD HARMLESS ATKINSRÉALIS, ITS OFFICERS, EMPLOYEES, DIRECTORS AND AGENTS FROM ANY AND ALL LIABILITY INCLUDING BUT NOT LIMITED TO LIABILITY FOR LOSS, DAMAGES, EXPENSES AND COSTS ARISING OUT OF OR IN CONNECTION WITH ENTERING AND/OR USING THE EXTERNAL WEBSITE AND/OR ANY LINKED WEBSITES AND ANY DATA AND/OR CONTENT CONTAINED THEREIN.
Such waiver and release specifically includes, without limitation, any and all rights and claims pertaining to reliance on the data or content of the External Website, or claims pertaining to the processing of personal data, including but not limited to any rights under any applicable data protection statute. You also recognize by clicking “Accept” that the terms of this disclaimer are reasonable.
The information provided by Virtua Research cited herein is provided “as is” and “as available” without warranty of any kind. Use of any Virtua Research data is at a user’s own risk and Virtua Research disclaims any liability for use of the Virtua Research data. Although the information is obtained or compiled from reliable sources Virtua Research neither can nor does guarantee or make any representation or warranty, either express or implied, as to the accuracy, validity, sequence, timeliness, completeness or continued availability of any information or data, including third-party content, made available herein. In no event shall Virtua Research be liable for any decision made or action or inaction taken in reliance on any information or data, including third-party content. Virtua Research further explicitly disclaims, to the fullest extent permitted by applicable law, any warranty of any kind, whether express or implied, including warranties of merchantability, fitness for a particular purpose and non-infringement.
The consensus estimate provided by Virtua Research is based on estimates, forecasts and predictions made by third party financial analysts, as described above. It is not prepared based on information provided by AtkinsRéalis and can only be seen as a consensus view on AtkinsRéalis' possible future results from an outside perspective. AtkinsRéalis has not provided input on these forecasts, except by referring to past publicly disclosed information. AtkinsRéalis does not accept any responsibility for the quality or accuracy of any individual or average of forecasts or estimates. This web page contains forward-looking statements based on current assumptions and forecasts made by third parties. Various known and unknown risks, uncertainties and other factors could lead to material differences between AtkinsRéalis' actual future results, financial situation, development or performance, and the estimates given here.
Downloads
Trade releases